New Section: Long-Term Reporting
Section 6 now:
Summarizes results for each metric, loss, delay delay var.
Discusses Long-Term Reporting
Measurement Intervals need not be the same length as “Long” Reporting Intervals (days, weeks, months)
Long Measurements come with some risks
Temporary power failure: loose results to date.
Timing signal outage invalidating some measurements.
Maintenance on the meas. system, or its connectivity.
Relatively Short Meas. Intervals can help to
match user session length
allow dual-use of measurements in monitoring activities