Done | Accept base protocol specification as a WG document | |
Done | Accept problem statement and applicability as a WG work item | |
Done | Start work with routing area WG(s) to undertake TRILL extensions | |
Done | Accept architecture document as a WG work item | |
Done | Accept routing protocol requirements as a WG work item | |
Aug 2006 | Submit architecture document to IEEE/IETF expert review | |
Aug 2006 | Submit routing protocol requirements to the IESG for publication as an Informational RFC | |
Aug 2006 | Submit problem statement and applicability to IESG for Informational RFC | |
Nov 2006 | Submit architecture document to the IESG for publication as an Informational RFC | |
Dec 2006 | Choose routing protocol(s) that can meet the requirements | |
Dec 2006 | Submit base protocol specification to IEEE/IETF expert review | |
Mar 2007 | Base protocol specification submitted to the IESG for publication as a Proposed Standard RFC | |
Jul 2007 | Re-charter or shut down the WG |